Projects can be divided into individual books. Books can be set up in Books Administration function.

pic_3589

Picture: Administration of Projects books

Book Contents

Book Index

Default settings

It is necessary to enter mandatory abbreviation and description if you insert new book (with Ins key).

pic_3590

Picture: Books of Projects - default settings

Description of Fields:

Edit reality

Tick the box to edit reality - Start Date and End Date of project as well as phases/activities and also Hours Worked on phases/activities.

Further it also allows to edit field Revenue and Costs of Project and phases/activities.

Edit planned prices

Tick the box to edit field Planned Revenue and Planned Costs of Project and phases/activities.

Double confirmation of phases/activities

If double confirmation is on, then first confirmation (yellow bi-map) of phase/planned activity confirms assigned resources (it's not possible to create Worksheets) and item data are not accessible. It's possible to create handover protocols. Handover protocols cannot be created after second confirmation.

Double reporting (reported/real)

When this option is ticked field Reported Actually appears next to Reported Effectively field (at phases/activities and worksheets)

Prices including VAT

If not checked price resources without VAT will be used, if checked then price resources with VAT are used.

Allow to report above plan

Tick the box to allow to report more work than it's been planned. If not ticked then it's possible to report work only up to what has been planned.

Confirm worksheets automatically

When worksheet is created and saved it'll automatically be also approved.

Automatic numbering of phase/activities

If checked, then when adding new phases / activities to the project, these stages / activities are automatically numbered. The number is saved in the Stage / activity code field.

Unit

Unit chosen here will then be auto-filled when entering new phase/activity in field Unit.

Calendar

Calendar is used for project planning - to suggest planned start and end dates for activities.

Usage (%)

It's used for from-to time planning for phases/activities as per planned time. For example if duration for phase/activity is set to 10 days and usage is 50% then it's planned for 20 days (Planned start date and planned end date).

Basic price type

Price type, which will be used for calculation of planned prices (costs and revenue), is entered here. If data is filled here then it must be also at price resources to allow calculation of planned prices. If data is not filled then it cannot be either at price resources.

Use terms from subordinate Phases/Activities and Assigned Resources

By this set up we can influence whether planned terms, when being changed, will also be supplied to superior Phases/Activities.

Type of invoicing

When creating a new project, the invoicing type entered here is pre-filled in.

Project members

 

Project role - project manager

Selection from Project roles code list. If entered then after filling Manager field on page 1 of the project, project manager will also be auto-filled with this project role to Project Members section.

Project role - project manager at customer

Selection from Project roles code list. If entered then after filling Manager of Customer field on page 1 of the project, project manager of customer will also be auto-filled with this project role to Project Members section.

Project role - Assigned project resource

Selection from Project roles code list. If entered then after filling assigned resource at phase/planned activity, it will also be auto-filled with this project role to Project Members section.

Book Contents

Book Index

Project Roles

Before project management starts it's necessary to set up Project roles. Projects roles have a list of authorizations which member with this role has in given project.

pic_3511

Picture: Project Roles

New project role is set up with Ins or F6 key. It is necessary to enter Name of role and assign rights to specific project role.

pic_3512

Picture: Project Roles - page 1

Description of Fields:

Name

Name of project role.

Responsibility

List of all responsibilities of given project role.

Rights

List of rights of given project role.

Book Contents

Book Index

Rights description of project roles

Browse project

Allows user to browse projects in which he/she is assigned as a project member (via linked contact person).

Change project

It allows user to enter Change of unconfirmed project.

Edit project partners

User has right to edit Project Partners on page 1 of the project.

Edit project members

User has right to edit Project Members on page 1 of the project.

Confirmation of phase, planned activity and milestone - all

It allows user to confirm all project phases.

Confirmation of phase, planned activity and milestone - owner

It allows user to confirm project phases in which he/she is set in Responsible field.

Confirmation of phase and planned activity resource - all

It allows user to confirm all resources assigned to project phases.

Confirmation of phase and planned activity resource - owner

It allows user to confirm resources assigned to phases, in which he/she is set in Responsible field.

Change project resource prices

User has right to edit Project Resource Prices on page 1 of the project.

Browse job queue - all

It allows user to browse all records of job queue at projects in which he/she is assigned as project member.

Browse job queue - owner

At projects in which user is assigned as a project member it allows him/her to browse following job queue records:

  • those at which he/she is set as person,
  • those at which summing source without specific person is shown and resource with contact person linked to user is included in this summation source in Project Resource codebook,
  • those at which vehicle is shown in resource type.

Browse worksheet - all

It allows user to browse all worksheets at projects in which he/she is assigned as project member.

Browse worksheet - owner

It allows user to browse worksheets at projects in which he/she is assigned as project member:

  • those at which he/she is set as person,
  • those at which vehicle is shown.

New worksheet

It allows user to create new worksheet for himself/herself or for a vehicle.

Change worksheet - all

It allows user to change all worksheets at projects in which he/she is assigned as project member.

Change worksheet - owner

It allows user to change worksheets at projects in which he/she is assigned as project member:

  • those at which he/she is set as person,
  • those at which vehicle is shown.

Confirm worksheet - all

It allows user to confirm all worksheets at projects in which he/she is assigned as project member.

Confirm worksheet - owner

It allows user to confirm worksheets at projects in which he/she is assigned as project member:

  • those at which he/she is set as person,
  • those at which vehicle is shown.

Create worksheet - all

It allows user to create worksheets for any person or vehicle at projects in which he/she is assigned as project member.

Book Contents

Book Index

Project resources

Project Resources book is used to register resources for project realization. Here we set up basic resource data and prices.

pic_3513

Picture: Project Resources - book

Data, related to resource with locator, are displayed in right pane. They are displayed for time period which is defined with range of items and in selected time unit.

Book Contents

Book Index

Basic Data (page 1)

pic_3595

Picture: Project Resource - basic data

Description of selected fields:

Type

Selection from user-defined code list.

Summing

Summing resource is an abstract resource that is used only for summary monitoring of requirements of defined subordinate resources. You can set both, physical resources and groups of resources as the itemized resources to a summing resource. Summing resource cannot be a group of resources at the same time. In the book record is indicated by icon pic_450i Resource with this marking cannot be entered to project.

Group

Group of resources. In the book record is indicated by icon pic_246i.png

Cost Centre

Select cost centre from codebook.

Resource type, Resource

In Resource Type field we select 'Contact person’, 'Vehicle’ or 'Article’. Then apart from resource type we can select also specific information.

When new resource with resource type Vehicle or Goods is set, check option Report in Quantity Unit is automatically pre-filled.

Report in Quantity Unit

If the field is checked quantity in Worksheets is filled in quantity unit (e.g. km are reported for vehicles). If the field is not checked, times is reported.

When invoicing in quantity unit it's necessary to have Report in Quantity Unit checked at source and at the same time the quantity unit must be at source included among warehouse units for assigned goods (field Goods(abbreviation 1)) at source.

Time unit

Time unit in which the source is planned the most. It's entered at sources which don't have Report in Quantity Unit attribute checked.

Quantity Unit

Quantity unit in which the source is planned the most. It's entered at sources which have Report in Quantity Unit attribute checked.

Calendar

Calendar indicates amount of resource which we have available during certain time period

Usage

Percentage of resource usage impacts only view in Capacity plan tab. If resource utilization gets above defined value - colour will change.

Goods (abbreviation1)

This information - the goods - is at invoicing filled in sales item of created issued invoice.

Subordinate resources are defined at resources with Summing or Group options at basic info tab. Subordinate resources part is displayed only at these resources (summing, group). Resources book opens to select subordinate resource after pressing INSERT in subordinates resources part.

pic_4339

Picture: Summing resource - basic data

Book Contents

Book Index

Items (page 2)

In Resource prices tab we can add costs and sales price to resources (in time or quantity unit) with validity from certain date and in selected currency. Price type can be defined at price. Price type (resource prices, which have this price type) which is defined in project book settings is used when calculating planned project costs and revenue. Price type is not being filled if it's not filled in Projects book settings either.

pic_4340

Picture: Resource prices

After pressing INSERT in change regime data should be entered in Resource price form:

pic_3597

Picture: Resource prices form

Book Contents

Book Index

Job queue

Job queues and worksheets which belong to period defined in right pane - in range of items, are displayed in Job Queue tab. Data here are to read only, it's not possible to edit them.

pic_4551

Picture: Projects - job queue

Book Contents

Book Index

Worksheets

Worksheets tab displays all worksheets of given resource and from here also column Reported is calculated to Capacity plan tab.

pic_4916

Picture: Worksheets for given resource

Book Contents

Book Index

Capacity Plan

Capacity plan of resource is overview of all total capacities, requests, available capacity and resource utilization. Data are shown for selected period according to range of items in right pane with option to sort them according to aggregation type (days, weeks, decades, ..). Time information are displayed according to selected time unit (day, hour, minute, week)

pic_4552

Picture: Resource capacity plan

Columns Description:

Abbreviation

Abbreviation for period according to selected aggregation type.

Capacity

Total resource capacity which is calculated from defined resource calendar.

Requests

Requests are uploaded from job queue.

Reported

Values in Reported are uploaded from worksheets.

Abbreviation

Time unit in which data are displayed.

Resource utilization

Graphic display of resource utilization in given period. Colour can change according to Utilization field set up in basic data. If utilization gets above current set up (overload), displayed colour will change.

In Resource preview black cross is displayed if at least one item shows capacity lower than required (according to percentage of Resource Utilization set at page 1 of resource):

pic_4602

Picture: Resource preview at overload of some of the items

Book Contents

Book Index

Documents (page 9)

 It is possible to add documents and assign references to the documents within theK2 IS in page 9 of Resources.  Closer description of work with notes is stated in The Basic Code Lists and Supporting Modules K2 – 9th page chapter.

Book Contents

Book Index

Project Calendar

Calendars which are used to monitor project resource capacity are defined in Project Calendar book.

Calendar range can be set up in lower right hand corner. This set up has influence on edit option of calendar items. Items cannot be edited outside of defined period.

pic_4544

Picture: Project Calendar

Book Contents

Book Index

Basic Data

pic_4545

Picture: Project Calendar - basic data

Description of Fields:

Abbreviation, Description, Type

Basic Information about Calendar.

Calendar basic data

 

 

Work regime

Selection from calendar regimes code list.

 

Weekly working hours

Average number of working hours per week.

 

Daily working hours

Average shift duration.

 

Number of shifts / week

Average number of shifts per week

 

Break

Break duration

Shift data according to defined date

Counts according to set year, payroll period and calendar week are displayed.

 

Year

Total hours per year (according to set range of items)

 

Month

Count of hours per month (according to set date in month)

 

Week

Count of hours per week (according to set date in week)

Display Calendar button is used to open Calendar component, where individual generated shifts are displayed. You can go through calendar month by month. If more items are entered for one time period then only the one with higher priority is displayed.

pic_4546
Picture : Project Calendar - displayed shifts

Book Contents

Book Index

Definition items

These are used for mass capacity definition in chosen time period. Individual calendar items (shifts) are generated by entering definition item.

pic_4547

Picture: Calendar definition items

Item data can be changed (Enter in Change status) only if interval of item creation is within defined range of calendar items.

Definition items are entered via Insert key.

pic_4548
Picture: Definition item

Description of Fields:

Item Type

Type of item can either be ‘time fund’ or ‘Day’.

Description

Description of calendar item. This is mandatory field.

Priority

Selection from priorities code list. Via priorities we can set superior or subordinate relationship of items. We must add record type ‘Day’ with higher priority to suppress all other items.

Description

Description of calendar item.

Type of time period

Selection of time period type or day. Field has only informative meaning.

Duration

Duration of time period in hours.

More

Specification related to entered change can be defined via button More. What kind of change it is etc.

pic_4550

Picture: More

Method of repetition when creating items

Here we define method of repetition of calendar item. How often the item should repeat in specified range.

Accepted days when creating items

Selection of in which days the items will be created.

Interval of automated items creation

Determination of interval in which calendar items will be created.

Resource count

Count of resources which we have available for given time period.

 

 

Book Contents

Book Index

External calendars

This page contains additionally added calendars. It's possible to add any other calendar as well as Holidays and special days calendar. Most often external calendar is added to suppress items of own calendar for certain period or days.

Capacity suppression is managed by specified priority of items. Items with higher priority override lower priority items. Items with ‘Day’ type take precedence over items with ‘time fund’ type with the same priority.

Calendars are entered via Insert key.

pic_4549

Picture: External calendars